The Village of Sag Harbor has started work on a new boardwalk along its waterfront. Staging for construction began on Nov. 10, and the village has set a finish date of April 1, 2027, or 120 days from the start of construction, whichever comes first. That puts the new walkway in place before the spring and summer crowds return to the harbor.
The project runs through John Steinbeck Waterfront Park, the open green on the water at the foot of Main Street, between Long Wharf and the bridge to North Haven. The village shared the work in a letter to residents from the mayor and Board of Trustees, along with the landscape design drawings that show where the boardwalk goes.
What the plans show
The design drawings lay out an 8-foot-wide boardwalk running through the park and tying into the stretch of boardwalk that is already there. Three seating areas sit along its length, with a picnic area marked near the end of the route.
The drawings place the route alongside several landmarks a Sag Harbor regular will know:
- The Windmill, the village's replica windmill at the head of Long Wharf, which serves as an information booth in season.
- Windmill Beach, the small sandy beach beside it where families let children wade.
- The LCpl Jordan C. Haeter Memorial, honoring the Sag Harbor Marine who was killed in Iraq in 2008.
- Ferry Road, the road that leads from the park toward the bridge.
The plans also call for clearing invasive plants from parts of the park. Native plants already growing there are to stay, and the cleared ground is to be planted as a native pollinator meadow, the kind of planting that feeds bees and butterflies through the warm months.
What to expect while it is built
The village told residents to expect more activity around the park over the winter: construction equipment, stacks of materials and crews on site. Access to some parts of the waterfront may be limited for stretches while work is underway. The village said it is working with its engineers and contractor to keep the work safe and to keep disruption to the surrounding area down.
Anyone walking the waterfront this winter should plan on following posted detours around the work zone.
Next door this week
Just across from the work zone on Long Wharf, Bay Street Theater is in the final week of its fall production of Aaron Sorkin's stage adaptation of To Kill a Mockingbird, directed by Stephen Hamilton, which runs through Nov. 29. The theater's box office is at 631-725-9500.
Where to get updates
The village is posting project updates on the Village of Sag Harbor website, where the letter to residents and the design drawings are also available. Questions about the work can go to the Village Office at (631) 725-0222, at 55 Main Street.