Work has started on the small wooden mill beside the pond in Roslyn's Gerry Pond Park. The Town of North Hempstead has started a $147,987 preservation project at the Roslyn Paper Mill, according to the Roslyn Landmark Society, which has been following the work since crews arrived in early November.
What the crews are doing
The project covers the parts of the site people actually walk on. It brings new stairs, new walkways and new handrails, along with drainage work around the building, which sits low beside the water. It also reopens a staircase on the property that has been closed to visitors for several years.
The Landmark Society first reported crews on site on Nov. 3, repairing the steps and improving drainage, and posted an update on Nov. 20 describing the full scope. The work follows improvements the town began in 2023 under its capital plan, which covered the building's roof and other parts of the structure.
The water wheel comes next
The mill's water wheel is not part of this phase. The town plans to restore it as a separate job and intends to put that work out to bid again in 2027, according to the Landmark Society.
Why a replica matters here
The building standing today is a replica, built in 1915 by Harold Godwin, the grandson of the poet and newspaper editor William Cullen Bryant, when the park was laid out. It stands on the site of the original mill, which the Onderdonk family operated beginning in 1773 and which was the first paper mill in New York. During the American Revolution that mill supplied paper for Hugh Gaine's New-York Gazette. The original building collapsed in a winter storm in 1906, and Godwin's replica went up nine years later.
A second mill project down the road
The paper mill is not the only one being worked on. The Roslyn Landmark Society is separately restoring the Roslyn Grist Mill with $2 million from Nassau County, and hopes the building will eventually serve as an education center for young people.
Visiting
Gerry Pond Park sits along Old Northern Boulevard in the center of Roslyn village, a short walk from Main Street and the clock tower. The Landmark Society expects the new stairs and walkways to make the path through the park easier for people on foot. The town has not published a completion date for this phase. The Landmark Society, which holds its annual meeting on Nov. 24, posts updates on its news page and can be reached at 516-625-4363.